Headlines via Reuters on further disruptions ahead:
-
Australia union: serves further notice of protected industrial
action at Chevron’s Gorgon and Wheatstone LNG projects in Australia - Australia union: new protected industrial action notice will escalate work bans, will
have rolling 24 x 1 hour stoppages each day for 14 days from Sept 14 - Australia’s offshore
alliance union says lawyers have served Chevron with further notice
of protected industrial action which will commence after first 7 days
of PIA kicks off on 7th September - Offshore alliance
union says new protected industrial action notice will escalate work
bans and the OA will have rolling 24 x 1 hour stoppages, each day for
14 days from Thursday 14th September
Wheatstone LNG Australia